Sam Rayburn Dam-Rate Order No. SWPA-84
Issued by Energy Department
What the record says
The Administrator, Southwestern Power Administration (Southwestern), has confirmed, approved and placed into effect on an interim basis Rate Order No. SWPA-84 (Rate Order), which provides the rate schedule Wholesale Rates for Hydro Power and Energy at Sam Rayburn Dam and Reservoir (SRD-23). This new rate schedule for the Sam Rayburn Dam and Reservoir (Rayburn) replaces the existing power rate under Rate Schedule SRD-15 which expires on September 30, 2024. Rate Schedule SRD- 23 increases the annual wholesale power rate for Rayburn by 21.1 percent.
This is a factual description of what was issued or decided, not an assessment of it.